An MVHR system should not be accepted simply because the unit powers on. This practical UK handover guide explains what an installer should check, measure and explain before completion, including design airflow rates, balancing, ductwork, controls, filters, noise, commissioning records and warranty information. Keep the checklist with your home documents and revisit it during servicing, property transactions or whenever the system’s performance changes.
Overview
Mechanical ventilation with heat recovery (MVHR) is designed to provide continuous fresh-air supply to habitable rooms while extracting stale, humid air from areas such as kitchens, bathrooms and utility rooms. The heat exchanger transfers energy between the outgoing and incoming air streams, but the system can only perform as intended if it has been correctly designed, installed, commissioned and maintained.
Commissioning is the process of checking and adjusting the completed installation so that it delivers the airflow the design requires. Handover is the point at which the installer records the results, explains operation and gives the homeowner the documents needed to use and maintain the system. These are different from a basic demonstration or an electrical power-up test.
Requirements depend on the property, system design, manufacturer and applicable Building Regulations guidance. In England, the ventilation provisions in Approved Document F may be relevant; other UK nations have their own technical guidance. Your installer should identify the requirements that apply to the project rather than relying on a generic checklist. Manufacturer instructions should also be followed, particularly for minimum clearances, filter types, controls and servicing.
For wider context on system selection, see MVHR vs PIV vs extractor fans. An MVHR handover checklist is most useful when it compares the completed installation with the approved design, not when it merely confirms that equipment has been fitted.
What to track
1. Design information and system identity
Ask for a copy of the ventilation design information or commissioning sheet. It should identify the MVHR unit, property or dwelling, relevant rooms, intended operating modes and design airflow rates. Record the unit’s make, model and serial number, installation date, installer details and any control accessories.
Check that the system layout broadly matches the design. Supply terminals should serve the intended living and sleeping spaces, while extract terminals should be located in moisture- or pollutant-producing rooms. If a room has been added, removed or substantially altered during construction, ask whether the ventilation design and airflow schedule were updated.
2. Measured supply and extract airflow
The installer should measure airflow at each relevant terminal using suitable test equipment and record the readings. The schedule should distinguish between supply and extract terminals and identify the operating condition used for each test, such as normal or boost mode.
Do not settle for a single airflow figure at the central unit. A unit can show an apparently plausible total while individual rooms receive too much or too little air. Ask for room-by-room readings, the target or design value, the measured value and any adjustment made.
3. Balancing and controls
Balancing means adjusting the system so that each terminal receives the intended airflow while the overall supply and extract arrangement remains appropriate. The handover record should show whether balancing was completed and whether any readings could not be achieved.
Check that normal, boost and any reduced or away settings operate correctly. The installer should demonstrate wall controls, wireless controls, humidity or occupancy sensors, boost switches and cooker-hood arrangements where fitted. Ask what each setting does, how long boost runs and whether a manual reset is required.
4. Ductwork and installation quality
Before ceilings, boxing or access panels are closed, inspect accessible ductwork. Look for supported runs, secure joints, insulation where specified, appropriate bends and no obvious crushing or kinking. Flexible duct should not be left compressed or loosely coiled when the design requires a smoother route.
Ask the installer to confirm that ducts are clean, connected to the correct terminals and sealed at joints. The unit should be accessible for filter changes and servicing. External intake and exhaust grilles should be unobstructed and positioned so that the system is not likely to draw in its own discharged air or exhaust into an unsuitable location.
5. Noise, air movement and comfort
Listen to the system in normal and boost modes, preferably with internal doors closed as they will be used. Note unusual vibration, rattling, whistling or excessive airflow noise. A small amount of background sound may be normal, but persistent noise can indicate a restriction, loose component, excessive air velocity, poor terminal adjustment or an installation issue.
Record any comfort concerns before sign-off. Do not close or tape over terminals to reduce noise, as this changes the designed airflow. Raise the issue with the installer and request a measured adjustment or explanation.
6. Filters, condensate and user information
The installer should show where the filters are located, how they are removed, which way they fit and what replacement specification the manufacturer requires. Ask how often they should be visually checked and replaced under the conditions of your home. A blocked filter can reduce airflow and increase strain on the system.
Where the unit produces condensate, confirm the drain route, trap arrangement and what to inspect if water appears near the unit. You should receive operating instructions, cleaning guidance, fault indicators, contact details for support and information about isolation switches. Keep the manuals accessible rather than storing them inside a sealed service void.
7. Handover documents
Request a complete handover pack containing, where applicable:
- the final commissioning sheet and room-by-room airflow readings;
- the design or installation information and any recorded changes;
- the MVHR unit model, serial number and control details;
- user and maintenance instructions;
- filter and condensate guidance;
- relevant electrical, installation or compliance records;
- warranty terms, start date and exclusions;
- installer and manufacturer contact details; and
- evidence of any required notification, certification or scheme documentation.
Not every document is issued in the same format for every project. If the installer says a particular certificate is not applicable, ask them to explain what record demonstrates completion and compliance instead.
Cadence and checkpoints
Use the following schedule as a practical home record, while giving priority to the manufacturer’s maintenance instructions and any service agreement.
- At handover: photograph the unit, filters, controls and accessible ductwork. Save the commissioning sheet, manuals and warranty information in both paper and digital form.
- After the first few weeks: note noise, condensation, draughts, odours and whether boost controls respond as expected. Report faults while the installation is still recent.
- Monthly or quarterly: inspect filters according to household conditions, check that terminals and external grilles are clear, and record any warning lights or unusual sounds. Homes with pets, building work or high dust levels may need more frequent checks.
- At least annually, or as the manufacturer specifies: arrange appropriate maintenance or review. Check that airflow settings have not been changed without a record and that the condensate route remains sound.
- After building work: repeat relevant checks if walls, ceilings, doors, windows or room layouts have changed. Dust from renovation can affect filters and ducts, while altered air paths can affect system balance.
Landlords should retain commissioning and maintenance records with the property file and provide occupants with clear operating information. A useful companion is this ventilation inspection checklist for rental properties.
How to interpret changes
A gradual increase in noise or weaker airflow may point to dirty filters, a blocked terminal, a closed internal door without an adequate transfer path, or a developing mechanical fault. Start with the safe user checks in the manual. Do not dismantle the unit, alter balancing dampers or change programmed airflow rates unless the manufacturer or a suitably qualified technician advises you to do so.
Condensation on windows is not, by itself, proof that the MVHR unit has failed. Consider moisture production, drying laundry indoors, cooking, bathing, cold surfaces and whether extract terminals are operating. However, persistent condensation, mould, stale odours or visibly poor airflow justify a professional investigation. Keep a short log of dates, rooms, weather, control settings and observed symptoms; this gives the technician useful evidence.
If measured airflow differs materially from the original record, ask for a diagnostic assessment rather than accepting a blanket increase in fan speed. Higher speed can increase noise and energy use without correcting a disconnected duct, blocked filter, poor seal or incorrectly set control. For practical humidity measures, see how to measure indoor air quality at home and how to reduce humidity when drying clothes indoors.
When to revisit
Revisit this checklist whenever the system is commissioned, serviced, repaired or altered. It is especially important before accepting a new-build or renovation handover, after replacing the MVHR unit, before selling or letting the property, and after work that changes the building envelope or room use.
Set a recurring calendar reminder for monthly or quarterly visual checks and an annual document review. Compare the latest filter condition, symptoms and service notes with the original handover record. If readings, controls or room use have changed, request an updated commissioning record rather than editing the old one.
Before signing off, walk through this final action list:
- Obtain room-by-room supply and extract readings.
- Confirm that the readings relate to the approved design and identified operating modes.
- Check accessible ductwork, terminals, grilles, filters and condensate arrangements.
- Test normal and boost controls and note how faults are indicated.
- Listen for unusual noise and record unresolved issues in writing.
- Save the commissioning record, manuals, warranty details and applicable compliance documents.
- Set the next filter inspection and maintenance reminders.
A clear handover protects the homeowner’s ability to operate the system correctly and gives future technicians a reliable baseline. If the installer cannot provide measured results or explain the system’s controls, pause final acceptance where possible and request clarification or a documented remedial plan.